Governor Alex Otti of Abia State has explained that a number of things contributed to the delay of the 181-megawatt geometric power plant in the Aba area of the state.
The $800 million project including the building 27km natural gas pipeline, championed by Geometrics Power Limited, has the capacity to generate and distribute 181 megawatts of power.
A new electricity distribution company, the Aba Power Limited Electric, has started taking electricity from the plant and supplying it to about nine of the 17 local government areas in the South-East state.
On Monday, Vice President Kashim Shettima inaugurated the geometric power plant in Aba, the industrial hub of the state.
The power plant which was described as the first integrated electricity facility in Nigeria is located in the Osisioma industrial hub of Aba in Abia.
Giving a background to the delay in the project, Otti, a former bank chief, said sometimes in 2010, the founder of Geometrics Power Limited and ex-Minister for Science and Technology, Bart Nnaji approached him as an Executive Director of First Bank to appeal that the former bank that was funding the project had stopped it mid-way owing to the global economic crisis.
The governor said the plant currently supply 141 megawatts power, the capacity at this time, is expandable to 181 megawatts when the final turbine is delivered.